Structured cabling services

Cablify designs and installs structured cabling for commercial buildings: copper and fiber from the point where service enters the building to every desk, access point and camera, labeled and documented so your IT team can support it for years.

Media
Cat6, Cat6A, multimode and single-mode fiber
Standards
ANSI/TIA-568, TIA-569 pathways, TIA-606 labeling, TIA-607 bonding
Testing
Fluke certification to the cable category
Systems
Hubbell Certified Installer
Closeout
Labels, port map and as-built drawings

The parts of a structured cabling system

A structured system is planned as one design, so every cable has a defined path, a defined end and a label that matches the records.

Parts of a structured cabling system in a three-floor buildingCarrier service enters at the entrance facility and reaches the equipment room on the ground floor. Backbone cabling rises to a telecom room on each floor. Horizontal cabling runs along each ceiling to outlets, Wi-Fi access points and cameras in the work areas.Backbone cabling: fiber and copper riserHorizontal cabling: Cat6 or Cat6A, 90 m maximumCameraTelecom room (IDF)one per floor or zoneAccess pointCameraTelecom room (IDF)patch panels and switchesHorizontal cablingto every outletCameraEquipment room (MDF)core switches, backbone patch fieldsWork areaoutlets and devicesEntrance facility: carrier fiber and copper enter the building here
How the parts connect in a three-floor building. Each floor has its own telecom room so no horizontal run passes 90 meters.

Entrance facility

Where carrier fiber and copper enter the building. We run from the carrier’s handoff to your equipment room and label the handoff point.

Equipment room (MDF)

The main room for core switches, firewalls and backbone patch fields. We install racks, ladder rack, patch panels and the bonding to the building ground.

Backbone cabling

Fiber and multi-pair copper from the MDF to every telecom room, through risers and sleeves, and between buildings on a campus.

Telecom rooms (IDFs)

One per floor or zone, placed so no horizontal run passes 90 meters. Each gets the same rack layout and labeling as the others.

Horizontal cabling

Cat6 or Cat6A from the IDF patch panel to each outlet, supported on J-hooks or tray and kept clear of lighting, sprinklers and ductwork.

Work area

Faceplates, outlets, access point and camera drops, and the patch cords that connect each device to its port.

Cat6, Cat6A or fiber

Most buildings use all three: Cat6 or Cat6A to the devices and fiber for the backbone. The choice affects speed, reach, PoE heat and the size of the pathways.

Cat6Cat6AMultimode fiber (OM4)Single-mode fiber (OS2)
Speed and reach1 Gb to 100 m; 10 Gb to about 55 m10 Gb to 100 m10 Gb to 400 m; 100 Gb to 100 m10 Gb to 10 km and beyond
Typical useDesks, phones, printersAccess points, cameras, labs, long-life spacesBackbone inside a building or campusBetween buildings and long campus runs
PoEYes; large bundles run warmerYes; handles heat in large PoE bundles betterNo, data onlyNo, data only
Cable sizeAbout 6 mm (0.24 in)About 7.5 to 9 mm (0.30 to 0.35 in)Many strands in one small jacketMany strands in one small jacket
Pathway impactStandard J-hooks and trayLarger J-hooks, more tray fill, bigger conduitInner duct or armored cable in shared spacesInner duct or armored cable in shared spaces
Copper figures are for the full 100 meter channel defined by ANSI/TIA-568. Fiber reach depends on the transceiver.

Plenum, riser and general-purpose cable

The National Electrical Code sets which cable rating can go where. A cable with a higher rating can always replace a lower one, so plenum cable is allowed everywhere. It also costs more, which is why we check the ceiling type on the walk-through and price the jacket each space actually needs.

CM-rated cable in a return-air ceiling fails inspection, and it is expensive to replace once the ceiling tiles are back.

RatingCopperFiberWhere it goes
PlenumCMPOFNPAir-handling spaces, such as return-air ceilings and raised floors used for air
RiserCMROFNRVertical runs between floors in shafts and risers
General purposeCMOFNOther spaces, such as runs inside conduit or open ceilings that are not plenums

Installation details we work to

These are the details that decide whether cabling passes certification and stays serviceable. They are written into our scope, not left to the crew on the day.

Pathways

J-hooks or tray at intervals of no more than 5 feet, sleeves through walls, and firestopping at every rated wall and floor penetration.

ANSI/TIA-569

Bend radius and pull tension

No tighter than four times the cable diameter for 4-pair copper, and no more than 25 pounds of pulling force, so the pair twist stays intact.

ANSI/TIA-568

Separation from power

Cable kept away from lighting ballasts, motors and transformers, and crossing power at right angles where it has to cross.

ANSI/TIA-569

Terminations

One wiring scheme, T568A or T568B, used on both ends of every link and across every floor.

ANSI/TIA-568

Labeling

The same identifier at the faceplate and the patch panel, matching the port map we hand over.

ANSI/TIA-606

Bonding

Racks, cabinets and ladder rack bonded to the telecommunications ground in each room.

ANSI/TIA-607

Testing

Permanent link tests with a Fluke certification tester to the cable category, with full reports when the project or a manufacturer warranty calls for them.

Fluke certification

Common questions

What does structured cabling cost?

It depends on the number of drops, the cable category, whether the ceiling is a plenum, ceiling height and access, the distance to each telecom room, testing and documentation requirements, and whether the work happens after hours. We price from drawings or a free site assessment and list each of these in the quote.

How many data drops does an office need?

A common planning figure is about one drop per 100 square feet of open office, with more in conference rooms and fewer in storage areas. The estimator on our home page uses these ratios. A walk-through sets the real count.

Do you certify the cabling?

Yes. Every link can be tested with a Fluke certification tester to its cable category. Full certification reports are supplied when the project calls for them, and manufacturer warranty programs require them.

Can you work with our general contractor and electrician?

Yes. On new construction and fit-outs we work to the general contractor’s schedule, agree pathways and back boxes with the electrician, and carry the low-voltage scope from rough-in to closeout.

How long does installation take?

It depends on the drop count, ceiling access and working hours. The quote includes a schedule, and in occupied buildings we phase the work by floor or zone so staff can keep working.

Request a structured cabling quote

Send the address, floor area and number of drops if you know it. Drawings or a reflected ceiling plan help us price the pathways.

Call 1-877-855-3865

Email

Free site assessments. Commercial work only.

We use your details only to reply to this request.